PPN003 Centre for Life – April to June 2019

The project is the construction of a new two-storey building inside of the Centre for Life building. The building accommodates a new ‘Creativity Studio’ where visitors are encouraged to participate in various making-oriented activities. The building comprises two classroom-type spaces, with wet areas and storage attached to each.

The M&E services generally were exposed and fixed directly to the new timber structure. This installation method required close attention to detail, finish quality and coordination for the M&E services and was a crucial part in the buildings finishing look. M&E Services included:

  1. Extension of live sprinkler system to new structure
  2. Extension of live fire alarm system to new structure
  3. Induction loop system
  4. Access control system
  5. Power, data, general lighting and emergency lighting systems
  6. Ducted VRF systems
  7. Domestics and drainage systems connected to existing